MIL-PRF-46676B (AR)
4.3. The samples shall be selected at random from a single production lot. Samples for tests
shall be taken in accordance with MIL-STD-1916, unless otherwise specified in Section 4.
4.1.2 Qualification inspection. Upon formal application, flexible explosive qualification
shall consist of specified tests for all requirements specified in Section 3, (see Table I).
4.1.2.1 Qualification rejection. If a product fails to meet any of the requirements
specified in Section 3, that product shall not be qualified, and shall not be listed on the QPL.
4.1.3 Conformance inspection. When specified, conformance inspection of product lots
shall consist of specified tests for all the requirements in Section 3 except for those indicated in
Table 2 to be not required.
4.1.3.1 Lot Formation A lot shall consist of one or more batches of flexible explosive in
accordance with the same processing operation, conditions, drawing, and specification. Lot
interfixing shall be in accordance with MIL-STD-1168.
4.1.3.2 Rejection of lots. If a product sample fails to pass any of the specified tests, the
production lot represented by that sample shall be rejected.
4.2 Support and ownership verification.
4.2.1 Form. Samples shall be taken from the production lot as specified and examined
using standard measuring equipment to verify form dimension and thickness requirements.
4.2.2 Color. A specimen shall be examined visually for conformance to paragraph 3.3.2.
4.2.3 Workmanship. The lot shall be visually inspected for any cracks, voids, air
bubbles, holes, blisters, dirt, and other impurities. Evidence of said impurities shall be cause for
lot rejection.
4.3 Operating verifications.
4.3.1 Detonation continuity. A sheet of explosive 0.08±0.004 inches by 3 inches by 10
inches shall be attached to a steel witness plate at least ¼ inch thick by means of adhesive
coating. The witness plate shall be large enough to back the entire slab of explosive. A military
M6 blasting cap or equivalent shall be secured against the middle of the 3 inch side of the
charge, and the assembly shall be mounted in a steel water tank capable of being pressurized to
10,000 psi. The charge shall be detonated after 45 minutes under a measured 10,000 psi
hydrostatic pressure, at ambient temperature. After detonation, the witness plate shall be
uniformly depressed and shall show no plateau indicative of a detonation discontinuity. A
discontinuity in detonation shall be cause for rejection.
5